How to protect steel without sacrificing looks or overpaying
Before getting into regulations, it is worth dispelling two widespread ideas about steel and fire.
The first is that steel melts in an ordinary fire. It does not: it melts above 1,400 °C, and in the regulations’ reference fire the air reaches about 1,000 °C after 90 minutes. What it does do is lose strength as it heats up. The second is that it is the material most vulnerable to fire, for example compared with concrete. That is a half-truth: an unprotected section heats up faster, but regulations require the same fire resistance from any structural material, and properly designed and protected steel meets it just as well.
That changes the question. It is no longer “which material is safer?”, but “how many minutes must this structure withstand, and how do we achieve it?”. And the answer is much easier to see today than a few years ago: modern intumescent paints are thin, smooth and can be finished in the project colour, so steel can stay exposed and be the star of the building, without the thick, rough coatings of the past.
But the most important part happens before painting. Effective protection starts with engineering: each member of the structure is calculated individually to know what it needs, how much product it should receive and how to comply with regulations without overspending.
Let’s start with the basics: what R30, R60 and R90 mean, what temperatures a structure actually reaches in a fire, what the regulations require and how it is solved in practice.

What do R30, R60, R90 and R120 mean?
Regulations set how long each element of the structure must withstand a fire. This requirement is expressed as an R (from résistance, load-bearing capacity) followed by the number of minutes:
| Class | What it means |
|---|---|
| R30 | The structure keeps its load-bearing capacity for 30 minutes |
| R60 | 60 minutes |
| R90 | 90 minutes |
| R120 | 120 minutes |
Time is measured against a reference fire that is the same for everyone (the ISO 834 standard curve), so every solution is compared on the same basis.
The EN 13501-2 standard uses three letters that should not be confused:
| Letter | What it guarantees | Where it is required |
|---|---|---|
| R | The structure keeps carrying its load | Columns, beams, floors, trusses |
| E | No flames or hot gases pass to the other side | Elements separating fire compartments |
| I | The unexposed side does not overheat | Compartment walls, doors and floors |
They are combined according to function: a beam or column is R; a wall separating compartments is EI; a floor that carries load and separates compartments is REI. Asking for “EI 60” for a beam is a common mistake in specifications and quotes: the correct requirement is R 60.
What temperatures does a structure face in a fire?
Higher than many people imagine. In the regulations’ reference fire, the air around the structure exceeds 550 °C in about 5 minutes, reaches 842 °C at 30, 945 °C at 60 and 1,006 °C at 90.
No structure is designed to withstand those temperatures unaided. That is why regulations do not ask “does it resist fire?”, but “how many minutes does it last before it gives way?”.
And here there is a very common misunderstanding. It is true that steel does not melt in a building fire (its melting point is above 1,400 °C), but it does not need to melt to fail: it loses strength as it heats up, like any other building material.
| Steel temperature | Strength retained (approx.) |
|---|---|
| Up to 400 °C | 100 % |
| 500 °C | 78 % |
| 600 °C | 47 % |
| 700 °C | 23 % |
| 800 °C | 11 % |
Reference values from Eurocode EN 1993-1-2.
Because a structure carries less load in a fire than in normal use, steel holds until it reaches its critical temperature, which is usually around 550 °C (a reference figure: it is calculated for each member). An unprotected section can reach it in a few minutes, around 10 to 20 depending on its size.
Fire protection does not make steel stronger: it delays its heating so that it does not reach that temperature before the required number of minutes.

Critical temperature of steel
Each member is calculated individually
This is what makes the difference: there is no “standard” protection thickness for R60. Two beams in the same building, under the same requirement, may need very different protection because two things change:
- The load each member carries in a fire: a lightly loaded member tolerates a higher temperature before failing.
- How “thick” the section is (section factor). Think of a thin steak and a thick one in a frying pan: the thin one heats up straight away. A slender section needs more protection; a heavy one, less.
That is why calculating each element separately is the key to good protection and an optimised budget: no over-protection (extra cost with no benefit) and no under-protection (a non-compliant structure). That is what our fire resistance design service does.
What about the connections? A structure is only as strong as its weakest point, and the connections, where beams and columns meet, are also checked for fire. The Eurocode devotes an annex to their behaviour and, when needed, they are protected along with the rest of the structure. We design and calculate them in our connection design service.
What fire resistance do regulations require?
The fabricator does not choose it: regulations set it according to the building use, its evacuation height and whether the element is above or below ground. In Spain there are two separate frameworks (in other countries, local regulations apply).
Non-industrial buildings: CTE DB-SI
Homes, offices, shops, hotels, schools and car parks are governed by table 3.1 of section SI 6:
| Use | Basement | Evacuation ≤ 15 m | ≤ 28 m | > 28 m |
|---|---|---|---|---|
| Single-family home | R 30 | R 30 | — | — |
| Residential, education, administrative | R 120 | R 60 | R 90 | R 120 |
| Commercial, public assembly, hospital | R 120* | R 90 | R 120 | R 180 |
| Car park (stand-alone building or above another use) | R 90 | |||
| Car park below a different use | R 120 |
*R 180 if the evacuation height exceeds 28 m.
Three nuances that can save a lot of money:
- Lightweight roofs. The main structure of a lightweight roof (self-weight up to 1 kN/m²) that is not used for evacuation and is less than 28 m high can be R 30 if its failure does not affect other floors, nearby buildings or compartmentation.
- Secondary elements. Mezzanines, stairs or lightweight floors whose collapse would not affect people, the stability of the building or evacuation may have no requirement.
- Evacuation height counts, not total height. It is the difference in level between the highest point people evacuate from and the building exit.
Industrial buildings and establishments: RSCIEI
Industrial buildings have their own regulation. Since 10 May 2025, Royal Decree 164/2025 has been in force, replacing the previous one (RD 2267/2004), and it is now fully mandatory for new projects. The same royal decree also amended the CTE DB-SI so that the two regulations fit together.
In an industrial building, the required R does not depend on height, but on three things:
- Building configuration: type A (shares the building with other establishments), type B (own building adjoining or within 3 m of others) or type C (own building more than 3 m away).
- Intrinsic risk level: low, medium or high, depending on the amount of combustible material manufactured or stored.
- Compartment location: basement or above ground, single or multiple storeys, lightweight roof or not.
A single-storey type C building with a lightweight roof is the most favourable combination, and active protection (such as sprinklers) can reduce the requirement further. That is why a well-planned logistics building may need far less protection than an office building of the same floor area. Defining configuration and risk properly at the start of the project is what saves the most money.
R30, R60 and R90 in real projects
The same structure may need R30 or R120 depending on where it is and what it is used for. Four examples under current Spanish regulations:
- Detached single-storey logistics building (RSCIEI). Own plot, type C, lightweight roof: the requirement depends on risk and active protection, and is often low or concentrated on specific elements. Here the key is not the paint, but the engineering beforehand. That is the approach behind our JANSPAN steel industrial buildings.
- Two-storey shopping centre (CTE). Commercial use with evacuation ≤ 15 m: R 90. Long column-free spans are steel’s natural territory. Columns and beams are protected with intumescent paint calculated member by member, and the lightweight roof can stay at R 30 if it meets the conditions.
- Ground + 4 apartment building with underground car park (CTE). Above ground, R 60; the car park below another use rises to R 120. Two protection levels on the same project, easily handled in the workshop: each member leaves with the thickness it needs. That is what we do in JANSBUILD steel-framed buildings.
- Eight-storey offices (CTE). Evacuation between 15 and 28 m: R 90. With intumescent protection applied in the workshop it is achieved without increasing section sizes, with lighter floors and open-plan floorplates, exactly what the office market wants.
How steel is protected: from thick mortars to thin paint
A few years ago, if you thought of fire protection, this probably came to mind: sprayed perlite or vermiculite mortar, a thick, rough, granular layer covering the section. It still exists and it works, but it is dense and unattractive, and usually ends up hidden behind a suspended ceiling or casing. Today there is a much thinner, cleaner alternative.
| System | How it works | Appearance | When it fits |
|---|---|---|---|
| Intumescent paint | Swells with heat and forms an insulating foam | Thin, smooth coat, colour finish | Exposed structure, R30 to R120, can be applied in the workshop |
| Sprayed mortar (perlite, vermiculite…) | Thick layer of insulating material | Rough and granular; usually hidden | Concealed structure, plant areas |
| Boards and panels | Box the section in with fire-resistant boards | Adds bulk, needs finishing | Columns and beams that will be clad |
| Specific construction solutions | Heavier sections or composite solutions, with technical justification | Depends on the design | Low requirements or composite structures |
Each system has its own application, finish and cost characteristics, and the choice depends on the project’s requirements. But when the aim is to keep the steel exposed, with a quality finish and parts ready to erect, intumescent paint applied in the workshop deserves special consideration.

Intumescent paint: thin, smooth protection in the colour of your choice
When cold, it is a thin paint. When the steel starts to heat up (from around 200 °C), it expands into an insulating carbonaceous foam that slows heat transfer to the section. With JANSFIRE this expansion can multiply the original thickness of the coat many times.
A fire-retardant paint, which slows flame spread across the surface, is not the same as an intumescent paint, which protects the structure from heat so that it does not fail.
Benefits:
- Protected structure without hiding its design. Exposed beams, columns and trusses, ideal for offices, shops, public spaces and industrial projects where steel is part of the architecture.
- A thin, even finish, with a topcoat in the project’s RAL colour.
- Protection tailored to each member. Thickness is set according to the section, the required R and the system’s certified performance.
- Applied in the workshop, with the structure ready to erect.
At Jansa Metal we offer JANSFIRE, our intumescent paint system applied in the workshop, with solutions of up to 120 minutes of fire resistance depending on the design and application conditions of each project. Outdoors or in humid environments it is combined with an anti-corrosion system and a sealing topcoat that protects the intumescent layer.
Why apply it in the workshop rather than on site?
Fire protection is part of fabricating the structure. Building it in from the start has clear advantages:
- Process control. Shot-blasted surface, stable environment and thicknesses checked member by member, without depending on the weather or other trades.
- Better planning. Protection fits into the fabrication schedule, with no separate subcontractor to coordinate on site.
- Careful finish. Controlled application conditions and an even finish.
- Less work on site. The structure arrives protected and ready to erect.

How we do it at Jansa Metal: from calculation to delivery
Fire protection is not an add-on to improvise once the structure is finished: it is part of engineering and fabrication. Our process:
- We define the required R according to the building use and the applicable regulations.
- We calculate each element in the fire situation (EN 1993-1-2): its critical temperature and section factor.
- We specify the paint thickness for each member, according to the selected system.
- We apply in the workshop: we prepare the surface (shot blasting) and apply the protection to the technical specifications.
- We check and deliver: we verify thicknesses and ship the identified parts, ready for erection.
The result is a solution coordinated from the design stage, with more accurate planning and direct control of the process.
Where money is made or lost
Fire protection is a small item in the budget if it is planned properly. Costly mistakes almost always come down to when decisions are made:
- Defining the R late. If the requirement appears once the structure is already fabricated, protection ends up being done on site, taking longer and with less control.
- Applying a single thickness. Using the worst-case section’s thickness across the whole project multiplies product use without improving safety.
- Confusing R with EI. It produces quotes that do not compare like with like.
- Forgetting the connections. They are also part of the structure and must be assessed.
Frequently asked questions
What does R60 mean for a structure? That its elements keep their load-bearing capacity for 60 minutes in the standard fire (ISO 834). In Spain it is the usual requirement for homes with an evacuation height of up to 15 m; for offices up to 28 m it rises to R 90.
What is the difference between R30, R60 and R90? The number of minutes the structure must withstand. The class you need depends on the building’s use and height or, for an industrial building, its configuration and risk.
What temperature does a fire reach and why does steel fail? In the reference fire, the air exceeds 550 °C in about 5 minutes and 1,000 °C at 90 minutes. Steel does not melt, but it loses strength as it heats up; that is why it is protected.
Do all beams and columns need the same paint thickness? No. It depends on the load and section factor of each section. Calculating each member avoids applying too much or too little.
Does every steel structure need protection? No. It depends on the required R and the calculation for each member. Some elements have no requirement (secondary elements, some lightweight roofs), and some low-requirement cases are solved with heavier sections. What you must not do is assume it: it has to be justified by calculation.
Does intumescent paint allow the structure to stay exposed? Yes. It is one of its great advantages: a thin, smooth finish with colour options, very different from the thick mortars of the past.
Can intumescent paint provide up to 120 minutes? Yes, there are systems designed for R120 under certified conditions. At Jansa Metal we offer JANSFIRE with solutions of up to 120 minutes, selected according to the project’s requirements.
Is it better to apply the paint in the workshop or on site? In the workshop, whenever possible: better thickness control, no dependence on the weather and the structure ready to erect.
Which regulations apply to an industrial building? In Spain, the Fire Safety Regulation for Industrial Establishments (RD 164/2025), in force since May 2025. Some warehouses with a low fire load may fall under the new Storage use in the CTE DB-SI; check according to your case.
Need to protect your steel structure against fire?
Safety, appearance and budget can go hand in hand when protection is properly planned.