Nobody mentions them in the quote. But everyone knows about them once it is too late. This is the list you will wish you had read before signing.

Every year, structural decisions that look right on paper turn into nightmares on site. The mistake is almost never in the calculations. It is in what nobody told you before you chose the building system.

Joan Juanola

MISTAKE No. 1: Calculating the construction schedule by counting only actual working days

When a developer or site manager draws up a programme, they usually plan the days needed to install the structure and move on. The mistake is forgetting the periods when the site is not ready, work cannot be done and so nothing progresses. That lost time is not just days piling up: it also breaks the rhythm of work. The inertia of restarting after every stoppage reduces the effective days, so we end up needing more working days than we would have planned without interruptions.

Some building systems mean that, once the structure is in place, no work can be done on that floor for weeks. Floors remain propped. Services, partitioning and finishing trades cannot start. The programme stretches, crane and scaffolding hire drags on, and late-delivery penalties start to loom.

Before choosing your structural system, ask yourself: how can the structure be erected without interruptions? How many days until the next trade can start work on it? That answer is worth more than any material price per tonne.

Dry erection systems let the other trades move in as soon as an area is erected. That keeps the time the structure holds up the site to a minimum.

MISTAKE No. 2: Pricing the structure without calculating the days lost between activities: foundations + structure + other packages.

Today more than ever, time is money. Every day on site means significant spending on resources and site overheads, but above all, the time spent on the structure has a direct and very expensive consequence: it sets the delay and cost of every other package on the project.

On many projects the structure accounts for no more than 20% of the total budget. And yet it can influence a large share of the cost of the other packages, a cost that would fall significantly if the structure were planned with time and precision as priorities.

The paradox is that the structural system is often chosen on material price, without considering the time and cost saved or added on the other packages.

The real cost of a structure is not what it weighs or what it costs, but the savings it generates in time and money. A structural system based on the effective time factor, well used, significantly reduces the cost of the whole project and makes every following package cheaper.

MISTAKE No. 3: Accepting that structural quality depends on the skill of the workers on site

In construction, there is a variable that rarely appears in contracts but determines the final result: the skill and competence of the workers carrying out the job

Systems built entirely on site, with mixes, pours, formwork and reinforcement assembled on the plot, introduce inherent variability that is hard to control. The result depends on the weather that day, the truck that arrived late, the experience of the tradesman and dozens of factors that do not appear on any drawing.

Systems fabricated entirely in the factory, in an industrialised process under controlled conditions, with precision machinery and formal quality inspections, eliminate that lottery. When the material reaches site, quality is already guaranteed. All that remains on site is assembly.

The question is not whether your supplier has good workers. The question is: how much of the quality process happens in the factory, and how much on site? The more that happens in the factory, the lower the risk on site.

MISTAKE No. 4: Choosing a structure that works on paper today but holds you back in reality tomorrow

A structure does not last five years. It lasts fifty or more. And what is a logistics building today may, in ten years, need changes, openings, mezzanines, canopies and so on. What is a storage unit today may need to become offices, laboratories or who knows what.

The mistake is choosing rigid structural systems that require columns every few metres or load-bearing walls that break up the interior. They solve today’s problem but rule out tomorrow’s options.

Modern construction demands open, flexible floorplates. Not just for looks, but because the way buildings are used changes. A system that can span long distances with slender sections turns any floor into a blank canvas that can be reconfigured without touching the structure.

What is it worth to have a structure that lets you extend, strengthen or modify the building in the future with minimal intervention? In the steel world, adding a level, opening a passage or strengthening a beam are operations a specialist team can carry out without demolishing anything.

MISTAKE No. 5: Ordering the structure without planning where the services will run

This is probably the mistake that causes the most frustration on site. And also the most avoidable.

The classic sequence goes like this: the structure is finished, the HVAC or plumbing team arrives and discovers that the beams or floors block the duct routes. Someone has to start chasing, drilling or improvising. The site manager argues with the trades, unplanned cracks or weaknesses appear, and nobody takes responsibility.

The cause is not anyone’s bad faith. It is the lack of a detailed engineering process before work starts on site. If the structure has not been drawn in 3D with the services inside before anything is fabricated, a clash is practically inevitable.

Building systems that force the whole geometry to be resolved before fabrication, because you cannot improvise in the workshop, are the ones that arrive on site without surprises. Beams can leave the factory with the necessary service openings and castellations, precisely calculated. Services pass cleanly through the structure, with no chasing or alterations.

It is a good example of how the “rigidity” of the workshop process is actually a huge advantage: it forces you to think everything through before you build. And that is exactly what separates a project that finishes on time from one that generates arguments until the last day.

With rigid systems, any future change means costly works, structural uncertainty and, in many cases, the decision not to do it. The building is frozen.

What these five mistakes have in common

None of them appears in the initial budget. They all appear later, when the project is under way and changing course is very difficult or impossible.

The good news is that they are all avoidable. The key is not the cheapest supplier or the best-known one. It is choosing a building system based on the EFFECTIVE TIME FACTOR that solves the problem before it reaches site: one that does not bring the site to a halt, does not burden the foundations, does not depend on luck outdoors, does not limit the building’s future and does not start wars between trades.

At Jansa Metal we have been solving exactly that for more than 40 years. If you have a project on the table, tell us about it.